Official Report WSP : Contruction Progress of Free Education Center East Aceh 17% [August 16, 2022]

8 comments

klen.civil
76
2 years agoSteemit3 min read
png_20220816_204627_0000.png

Site Clearing and Landing Altitude Measurement and Footing has been completed for the construction of the Free Education Center, the continuation of the main work items in the form of Post and Sloof has now also increased the construction progress of the building.Where the progress of the post has experienced 2% of the total, namely the installation of iron in that place. Meanwhile, the work that is currently being carried out by the workers is the iron work for the Post and sloof which is targeted to be completed in two working days. The casting of the two main work items will be carried out after the installation of iron in the area has been completed. For the total construction progress of the Free Education Center at this time is 17% of the total according to the analysis of Indonesian construction techniques.

NoType of WorkPersentase
1.Site Clearing and Landing Altitude Measurement5/5
2.Footing10/10
3.Sloof0/10
4.Round Floor Building0/8
5.Post2/15
6.Wall0/12
7.Beam0/10
8.Steel Truss Roof0/20
9.Painting0/5
10.Finishing0/5
Total Persentase17/100

So from a total of 10 main work items from the Free Education Center Construction for East Aceh whose funding source is from the World Smile Project INT, it can be concluded that the construction progress has reached 18% of the total which is marked by the completion of 4 work item, namely Site Clearing and Landing Altitude Measurement with 5%, and there is work being done in the form of footing which has progress of 10% and post 2% of 15% overall. And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :

Current condition of Free Education Center Development for East Aceh
IMG-20220816-WA0011-01.jpegIMG-20220816-WA0008-01.jpeg
Front ViewBack View
IMG-20220816-WA0007-01.jpegIMG-20220816-WA0009-01.jpeg
Right ViewLeft View
IMG-20220816-WA0006-01.jpegIMG-20220816-WA0005-01.jpeg
Another perspectiveAnother perspective
Other documentation is in the form of photos of workers in activity and on site materials
IMG-20220815-WA0021.jpgIMG-20220816-WA0012.jpg
IMG-20220816-WA0028.jpgIMG-20220816-WA0027.jpg
IMG-20220816-WA0004.jpgIMG-20220816-WA0001.jpg

This is the progress report on the construction of the free education center for East Aceh which has started today as of August 16, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.

The link to the previous post concerns the progress of the Free Education Center construction for East Aceh
  1. Official Report WSP : Contruction Progress of Free Education Center East Aceh 5% [August 5, 2022]

  2. Official Report WSP : Contruction Progress of Free Education Center East Aceh 12% [August 11, 2022]

Free Education Center Building Information for East Aceh (World Smile Project INT)
ProjectFree Education Center
TypeBuiding Contruction
Size or Dimention9 x 6 meter
AddressTanjong Punti village, Madat district, East Aceh
Benefit recipientsEarly Childhood
Teacher@steemitcountry

Cc : @pennsif @el-nailul @heriadi @irawandedy @mariana4ve @ubongudofot @patjewell @alanasteemit


East Aceh, August 11, 2022
@klen.civil
WSP Construction Supervisor

Comments

Sort byBest